August 12, Colombo (LNW): The Committee on Public Accounts (CoPA) has raised concerns over a significant increase in the bid for the Basnagoda Reservoir construction project.

The contractor’s bid of Rs. 2,093 million was raised by Rs. 254 million, reaching Rs. 2,347 million, based on recommendations from the Technical Evaluation Committee.

CoPA questioned the Irrigation Department’s payment processes, which reportedly did not comply with government financial regulations.

The committee highlighted that previous recommendations to rectify these procedures had not been implemented, prompting further scrutiny.

Additionally, CoPA examined irregularities involving 1,177 cheques worth Rs. 352.4 million issued in 2022, including issues with a Divisional Assistant improperly cashing payments.

The officials present admitted to calculation errors and double entries, assuring that corrective measures had been taken.

The Committee also discussed the Ging Nilwala project, which received an advance of 4.35% of the estimated cost, despite the project not commencing as planned.

The meeting was chaired by State Minister Lasantha Alagiyawanna and attended by several Members of Parliament.

Share post:

spot_imgspot_img

Popular

More like this
Related

Luxury bus deal faces scrutiny over tender issues

Luxury bus deal faces scrutiny over tender issues

Sri Lanka’s Tea Sector Brews Big Gains amid Global Shifts

Sri Lanka’s Tea Sector Brews Big Gains amid Global Shifts

Geopolitics and Commercial Clashes Delay Sri Lanka’s $3.7 B Sinopec Refinery

Geopolitics and Commercial Clashes Delay Sri Lanka’s $3.7 B Sinopec Refinery

Colombo’s Port City Crosses Major Infrastructure Milestone

Colombo’s Port City Crosses Major Infrastructure Milestone