Railway Restrictions Announced for Bujjomuwa Bridge Repairs

0
122

The Railway Department has announced that train operations between Ambepussa and Alawwa will be limited to a single track from April 1 to 5 to facilitate permanent repairs to the Bujjomuwa bridge.

The repairs follow damage caused by Cyclone “Ditwah,” which resulted in the collapse of an old brick arch culvert, creating a 45-foot cavity beneath the track.

Currently, trains are operating over a temporary bridge with a speed restriction of 10 kmph.

The department stated that from April 1 to 4, two trains operating between Colombo Fort and Rambukkana will be curtailed up to Ambepussa. Additionally, two Colombo Fort–Rambukkana trains scheduled for April 2 will be cancelled.

Passengers traveling on routes to Rambukkana, Mahawa, Trincomalee, and Batticaloa from Colombo Fort are advised to expect delays during the repair period.