Expert from China to arrive in SL to troubleshoot generator at Norochcholai

Date:

A Chinese expert is set to arrive in Sri Lanka to inspect the faulty generator at the Norochcholai Coal Power Plant, revealed the Ceylon Electricity Board (CEB).

Upon troubleshooting the machine, it would be possible to restore the generator out of order, said Chairman of the CEB M.M.C. Ferdinando.

Accordingly, a continuous capacity of 300 MW will be added to the national grid and then a continuous supply of electricity can be provided, he added.

The occasional power outages evident in the recent were mainly due to the collapse of power generation at the Plant. Hydrocapacity has also dropped and meanwhile problems have arisen at the Kelanitissa Thermal Power Plant as well.

Ferdinando added that there is no crisis regarding the application of coal required for power generation, for the CEB has the required stocks of coal until next May. Steps are being taken to import coal for the rest of the year, he added.

MIAP

Share post:

spot_imgspot_img

Popular

More like this
Related

Regulatory Uncertainty Threatens Foreign Investments amid Economic Fragility

Sri Lanka’s fragile investment recovery faces renewed pressure as...

Cyclone Shock Exposes Power Sector Fault Lines, CBSL Warns

The aftermath of Cyclone Ditwah did more than replenish...

Cyclone Ditwah Exposes Economic Fragility amid Policy Paralysis

Sri Lanka’s post-crisis economic recovery suffered a severe reversal...

China Pumps Millions into Colombo Port City as Policy Chaos Looms

China Harbour Engineering Company (CHEC) has doubled down on...