A Chinese expert is set to arrive in Sri Lanka to inspect the faulty generator at the Norochcholai Coal Power Plant, revealed the Ceylon Electricity Board (CEB).

Upon troubleshooting the machine, it would be possible to restore the generator out of order, said Chairman of the CEB M.M.C. Ferdinando.

Accordingly, a continuous capacity of 300 MW will be added to the national grid and then a continuous supply of electricity can be provided, he added.

The occasional power outages evident in the recent were mainly due to the collapse of power generation at the Plant. Hydrocapacity has also dropped and meanwhile problems have arisen at the Kelanitissa Thermal Power Plant as well.

Ferdinando added that there is no crisis regarding the application of coal required for power generation, for the CEB has the required stocks of coal until next May. Steps are being taken to import coal for the rest of the year, he added.

MIAP

Share post:

spot_imgspot_img

Popular

More like this
Related

Ceylon Dollar Bond Fund Shines amid Revival of Sovereign Confidence

Sri Lanka’s dollar bond market once battered by default...

Sri Lanka beer market balances tax burden with tourist-driven demand

Sri Lanka’s beer sector is navigating a delicate balance...

Expert Warns of dismantling tariffs and para-tariffs Risking  Economic Stability 

Sri Lanka must not rush into dismantling tariffs and...

Sri Lanka Tourism Booma, amidst Revenue Bust and : Mismanaged Agencies

Sri Lanka may be celebrating record-breaking tourist arrivals, but...