Sri Lanka’s efforts to restructure the electricity sector and restore the financial stability of the Ceylon Electricity Board (CEB) risk repeating longstanding policy mistakes unless the Government confronts the structural weaknesses that have driven electricity costs upwards for decades. The warning comes amid questions over the financial consequences of the ongoing restructuring process, rising tariffs, coal-related losses and the country’s continued dependence on expensive electricity generation.
Former Power and Energy Minister and electrical engineer Patali Champika Ranawaka has argued that the CEB’s financial performance reflects a combination of generation costs, system losses, management efficiency, capital expenditure, subsidies and tariff policies rather than the performance of individual ministers alone.
His assessment raises important questions about whether the Government’s electricity reforms are addressing the underlying causes of financial instability or concentrating excessively on institutional restructuring.
One of the most revealing aspects of Ranawaka’s analysis concerns the failure to give sufficient priority to electricity demand management. Sri Lanka traditionally concentrated on expanding generation capacity to accommodate rising consumption, often overlooking the economic advantages of reducing peak demand through energy efficiency and conservation.
The introduction of compact fluorescent lamps and LED lighting during 2011-12, together with initiatives implemented through the Sustainable Energy Authority, helped keep nighttime peak demand below 3,000 MW between 2010 and 2025.
This was significant because earlier projections had suggested that peak nighttime demand could exceed 6,000 MW as electrification expanded.
Ranawaka alleged that demand-management projects initiated in 2016 and 2026 had failed, raising questions about policy continuity, institutional coordination and the effective utilisation of public investment.
Failure to manage demand can force the country to invest in additional generation capacity, transmission infrastructure and expensive backup facilities, increasing the financial burden on the electricity utility and ultimately consumers.
The latest financial difficulties have also been complicated by the restructuring of the CEB into separate companies. Ranawaka attributed part of the utility’s 2026 losses to administrative disruption arising from this restructuring.
Although institutional reforms may improve accountability and operational efficiency, dividing an organisation does not automatically eliminate inefficiencies, procurement weaknesses or financial mismanagement. Without clearly defined responsibilities, transparent financial reporting and effective coordination, restructuring could create additional administrative costs.
Coal procurement has emerged as another serious concern. Ranawaka attributed part of the 2026 financial losses to substandard coal, highlighting the potential consequences of inadequate quality controls and procurement oversight.
Given the substantial share of generation costs in total CEB expenditure, weaknesses in fuel procurement can have far-reaching consequences for electricity production costs and the utility’s financial position.
Another concern is the role of favourable hydrological conditions in cushioning the electricity sector during 2025-26. Ranawaka maintained that abundant water availability had helped prevent substantially worse financial outcomes.
This raises a fundamental sustainability question: can the electricity sector remain financially stable when favourable rainfall conditions disappear and expensive thermal generation becomes necessary?
Meanwhile, consumers have already experienced substantial tariff fluctuations. Electricity prices increased nearly threefold during 2022-24, while Ranawaka claimed that tariffs rose by approximately 54 percent during 2025-26 under the present administration.
For households, manufacturers and small businesses, unpredictable electricity pricing complicates financial planning, increases production costs and undermines competitiveness.
The Government must therefore demonstrate that restructuring will deliver measurable improvements rather than merely change institutional structures.
Independent coal-quality monitoring, transparent procurement, demand-side management, realistic investment planning and predictable tariff policies should become central pillars of reform.
Ultimately, electricity-sector restructuring must be judged by whether it reduces generation costs, improves reliability and protects consumers—not by the number of companies created or the administrative changes announced.