Shut down Generator 02 at Norochcholai Plant to be restored today

Date:

Colombo (LNW): Generator Two at the Norochcholai Coal Power Plant, which was recently shut down due to maintenance work, will be restored and reconnected to the national grid at 8 pm tonight (15).

The Generator Two at the Plant was shut down on August 08 due to an issue, and about 270 megawatts were lost from the national grid as a result, the Ceylon Electricity Board (CEB) said.

Meanwhile, the Unit Three of the Plant was also shut down for a period of 100 days from June 13, for a scheduled major overhaul maintenance work, the CEB added.

Share post:

spot_imgspot_img

Popular

More like this
Related

Stalled Rail Projects Expose Deep Cracks in Public Sector Delivery

Sri Lanka’s infrastructure development drive has suffered another blow,...

Bloated Public Sector Drains Sri Lanka amid Skills Crisis

Sri Lanka’s public sector long criticized for inefficiency, political...

BOC Doubles Profit as Digital Push and SME Lending Drive 2025 Surge

The Bank of Ceylon has delivered a landmark financial...

New Office Tower Marks Turning Point for Port City

Sri Lanka’s flagship Port City Colombo development has gained...