Shut down Generator 02 at Norochcholai Plant to be restored today

Colombo (LNW): Generator Two at the Norochcholai Coal Power Plant, which was recently shut down due to maintenance work, will be restored and reconnected to the national grid at 8 pm tonight (15).

The Generator Two at the Plant was shut down on August 08 due to an issue, and about 270 megawatts were lost from the national grid as a result, the Ceylon Electricity Board (CEB) said.

Meanwhile, the Unit Three of the Plant was also shut down for a period of 100 days from June 13, for a scheduled major overhaul maintenance work, the CEB added.

Share post:

spot_imgspot_img

Popular

More like this
Related

Anti-Terrorism Bill’s Broad Secrecy Clause Threatens Public Oversight of Security Operations

Sri Lanka’s proposed anti-terrorism legislation has triggered another serious...

Untapped Women’s Talent Exposes Sri Lanka’s Economic Opportunity Gap

Sri Lanka's ambition to become a competitive regional investment...

SL Govt’s Security Bills Threaten Rights, Dissent and Sri Lanka’s GSP+ Lifeline

The Government’s proposed security legislation is rapidly developing into...

Exporters Face Regulatory Barriers despite Soaring Export Growth

Sri Lanka’s export sector is recording encouraging growth in...